Concrete Mix Ratio Calculator

A concrete mix ratio is the recipe that decides how strong your concrete ends up and how much it costs you. It is written as three numbers — cement, sand and coarse aggregate — measured by volume rather than weight, so 1:1.5:3 means one part cement to one and a half parts sand to three parts stone. ...

CEMENT : SAND : AGGREGATE

NOMINAL GRADE

::
cementsandaggregate

That is M20slabs, beams, columns in housing.

A ratio in the 0.40 to 0.60 band is the usual working range for hand-placed concrete.

CEMENT TO BUY

9 bags

8.47 exact · 50 kg each · 423.4 kg of cement

SAND

0.441 m³

AGGREGATE

0.882 m³

WATER

211.7 L

Dry batch volume

1.617 m³

Wet volume + wastage

1.050 m³

Cement weight

423.4 kg

Sand weight

706 kg

Aggregate weight

1,323 kg

Total dry weight

2,452 kg

Water

211.7 L

Yield per bag

0.124 m³

BATCHING IT

1

Order 9 bags of cement, 0.441 m³ of sand and 0.882 m³ of coarse aggregate.

2

Batch by volume in the ratio 1 : 1.5 : 3. One bag of cement is about 0.0347 m³, so use that as your gauge box.

3

Mix the cement and sand dry until the colour is even, then add the aggregate and turn it through.

4

Add water gradually to 211.7 litres in total. Stop at a workable slump — the last litre is the one that costs you strength.

THE BATCH

DRY MATERIALS SHRINK WHEN WETTED — SO YOU BATCH MORE THAN YOU POURYOU WANT1.05finished concreteYOU BATCH1.62loose dry materialCEMENTSANDAGGREGATE× 1.54the fines settle into the gaps between the stones, so the mix loses volumebatch to the right-hand column, pour the left

Why you batch 1.54 times the volume you want. Loose sand and aggregate are full of air. Once water is added, the cement paste and fine sand migrate into the gaps between the stones and the whole mass consolidates. Batching 1.617 m³ of dry material yields about 1.050 m³ of placed concrete. Skip this step and you finish roughly a third short.

WHAT TO ORDER9 bagsof 50 kg cement · 8.47 exactSAND0.441AGGREGATE0.882

Heap height is drawn to the cube root of volume, the way a real stockpile grows — a pile twice as tall holds eight times as much, which is why sand deliveries always look smaller than the number suggests.

HOW RICH IS THIS MIX?

NOMINAL MIXES — BAR LENGTH IS THE CEMENT SHARE OF THE DRY BATCHM51:5:10M7.51:4:8M101:3:6M151:2:4M201:1.5:3M251:1:2YOURS1:1.5:3above M25 a designed mix with tested materials is required, not a volume recipe

Live calculation · updates as you type

Created with❤️byeaglecalculator.com

HOW TO USE

  1. 1

    Enter the finished volume of concrete you need. That is the volume of the slab, footing or column once it is poured and compacted — not the volume of dry material, which the calculator works out for you.

  2. 2

    Pick a nominal grade, or type your own ratio into the three boxes. M20 (1:1.5:3) suits most domestic slabs and beams; M15 (1:2:4) is fine for paths and light foundations; M25 (1:1:2) is for heavier reinforced work.

  3. 3

    Set the water–cement ratio. Between 0.40 and 0.60 is the usual working range for hand-placed concrete. Lower is stronger but stiffer to place; higher is easier to work but measurably weaker.

  4. 4

    Read off the cement bags, sand, aggregate and water. Open site adjustments if you need to change the wastage allowance, the dry volume factor, or the cement bag size to match what your supplier actually sells.

THE FORMULAS

Dry batch volumeV_dry = V_wet × 1.54
Cement volumeV_dry × c / (c+s+a)
Sand volumeV_dry × s / (c+s+a)
Aggregate volumeV_dry × a / (c+s+a)
Cement weightV_cement × 1440 kg/m³
Bags of cementweight / bag size
Waterw/c × cement weight
Volume of one bag50 / 1440 = 0.0347 m³

NOMINAL MIX REFERENCE

GradeRatioApprox. strengthTypical use
M51:5:10~725 psiBlinding, levelling under footings
M7.51:4:8~1090 psiMass fill, non-structural bedding
M101:3:6~1450 psiKerbs, floor blinding, fence posts
M151:2:4~2175 psiPaths, patios, light foundations
M201:1.5:3~2900 psiSlabs, beams, columns in housing
M251:1:2~3625 psiRCC work, heavier structural members

Grade names give the characteristic cube strength in megapascals at 28 days — M20 means 20 MPa. The psi figures are the approximate imperial equivalents. Nominal volumetric mixes stop at M25; anything stronger needs a designed mix proportioned from tested materials.

FREQUENTLY ASKED QUESTIONS

RELATED CALCULATORS

MORE CONCRETE CALCULATORS

Was this calculator helpful?

Last updated: July 29, 2026 · Formula verified · Eagle-eyed accuracy for every calculation.