Concrete Path Calculator

A concrete path is the simplest slab there is to calculate and one of the easiest to get wrong in ways that only show up a year later. The volume itself is length times width times thickness, and if that were the whole job this page would not need to exist. What separates a path that lasts from one ...

THE PATH

SECTIONS — LEAVE LENGTH AT 0 IF UNUSED

CONCRETE REQUIRED

1.58

14.40 at 100 mm · including 10% waste · 3.80 tonnes

SUB-BASE

3.02 t

EDGING

24.0 m

JOINTS

6

Cut 6 joints, giving 7 panels. Spacing is set by panel shape rather than slab thickness, which is normal on a path — a panel much longer than one and a half times its width becomes a strip, and strips crack across their middle. That gives 1.8 m centres. Cut them within 24 hours of pouring, a quarter of the slab depth deep.

Total area

14.40 m²

Concrete before waste

1.440 m³

With 10% waste

1.584 m³

Weight

3.80 t

Sub-base compacted

1.440 m³

Sub-base to order

1.800 m³ loose

Sub-base weight

3.02 tonnes

Edging / formwork

24.0 m

Panels

7 at 1.71 m

Bags / loads

94 / 1

LAYING IT

1

Excavate to 200 mm below finished level and set 24.0 m of edge form, checking the fall as you go.

2

Lay and compact 1.800 m³ of sub-base in layers to a finished 100 mm. It arrives loose and settles about a quarter, so order the loose figure.

3

Place 1.584 m³ of concrete, working from one end and screeding off the forms. Lay a slight fall across the width so water runs off.

4

Cut 6 control joints within 24 hours, a quarter of the slab depth. Then keep it damp for several days — fast drying is what cracks a path.

THE PATH

PLAN — DRAWN TO SCALE, JOINTS MARKED12 m × 1.2 m7 panelsgold dashes are control joints — concrete cracks whether you plan for it or nota joint decides where, so the crack runs straight and stays closed

Concrete cracks. The only question is where. It shrinks as it cures and keeps moving with temperature afterwards, and a path is a long thin shape with nowhere for that movement to go. A control joint is a deliberate line of weakness that decides the answer in advance, so the crack forms straight, below the surface, and stays closed. Here that means 6 joints at 1.8 m centres.

SECTION THROUGH THE PATH — VERTICAL SCALE EXAGGERATED100 mmcompacted sub-base100 mmconcrete1.2 m widelay the surface with a slight fall to one side so water runs off rather than sitting on it

Sub-base is quoted as the finished compacted depth, but it is delivered loose and settles by about a quarter — so order 1.800 to finish at 100 mm, roughly 3.02 tonnes.

TWO WAYS TO SUPPLY IT+49 not drawn94bags of 80 lb1.581 load at 8.0

Live calculation · updates as you type

Created with❤️byeaglecalculator.com

HOW TO USE

  1. 1

    Enter the length and width of your path. If it changes width partway, or turns a corner into a different run, use the second and third section rows — leave their length at zero if you only have one straight run.

  2. 2

    Set the slab thickness. Seventy-five millimetres is enough for foot traffic only, a hundred is the general answer, and anything a vehicle will cross wants a hundred and twenty-five or more.

  3. 3

    Set the sub-base depth. A hundred millimetres of compacted granular material suits most paths; leave it at zero only if you are pouring onto genuinely firm, well-drained ground.

  4. 4

    Read the concrete, the sub-base as a loose order quantity, the edging length, and the control joint count. The joint figure is the one worth acting on — cut them within a day of pouring, a quarter of the slab depth deep.

THE FORMULAS

AreaΣ length × width
Concretearea × thickness × (1 + waste)
Sub-base compactedarea × sub-base depth
Sub-base to ordercompacted × 1.25
Sub-base weightcompacted × 2.1 t/m³
Edging2 × length per section
Joint spacingmin(24 × thickness, 1.5 × width)
Panelsceil(length / spacing)

PATH THICKNESS AND JOINT SPACING

UseWidthThicknessSub-baseJoints every
Garden path, foot traffic0.9 m75 mm75 mm1.35 m
General path1.2 m100 mm100 mm1.80 m
Wide path or side access1.5 m100 mm100 mm2.25 m
Occasional vehicle2.4 m125 mm150 mm3.00 m
Driveway grade3.0 m150 mm200 mm3.60 m

Notice that joint spacing tracks width rather than thickness in every row. Paths are narrow, so the rule that keeps panels near square binds before the one about slab depth does. On a wide slab it would be the other way round.